Milestones
Open
0
Closed
8
All
8
Due soon
Before First Sprint
Jon Shahen / ece651-project
Jan 21, 2019–Jan 27, 2019
Closed
7/7 complete
100%
Sprint 01
Jon Shahen / ece651-project
Jan 28, 2019–Feb 3, 2019
Closed
7/7 complete
100%
Sprint 02
Jon Shahen / ece651-project
Feb 4, 2019–Feb 11, 2019
Closed
7/7 complete
100%
Sprint 03
Jon Shahen / ece651-project
Feb 11, 2019–Feb 25, 2019
Closed
9/9 complete
100%
Sprint 04
Jon Shahen / ece651-project
Feb 25, 2019–Mar 4, 2019
Closed
3/3 complete
100%
Sprint 05
Jon Shahen / ece651-project
Mar 4, 2019–Mar 11, 2019
Closed
5/5 complete
100%
Sprint 06
Jon Shahen / ece651-project
Mar 18, 2019–Mar 25, 2019
Closed
8/8 complete
100%
Sprint 07
Jon Shahen / ece651-project
Mar 25, 2019–Apr 1, 2019
Closed
5/5 complete
100%